Renewable Energy

DTE Energy Seeks Up to 150 MW of New Solar Built in Michigan

Mina SatoNovember 22, 20265 min read0 views

At a glance

  • Bids are due Jan. 19, 2027, contracts are expected in mid-2027, and winning projects must reach commercial operation by June 30, 2030.
  • DTE Energy has opened a competitive solicitation for up to 150 megawatts of new Michigan-sited solar under a 2025 commission settlement, with a 2030 operation deadline. The utility says the projects would curb fuel-cost exposure and add local tax revenue, but it disclosed no sites, developers or cost figures.
Rows of ground-mounted solar panels on flat farmland at sunset, with a transmission pylon and power line crossing the sky behind the array.

DTE Energy has opened a competitive procurement for up to 150 megawatts of new solar generation sited in Michigan, a move the utility says will create construction jobs, support host communities and save customers money on fuel.

Because solar plants do not burn fuel, DTE said the additions would reduce its exposure to fuel-price swings over the projects' operating lives. The company presented the procurement as part of its effort to supply power that is reliable, increasingly clean and affordable.

Fuel savings and community benefits

According to the company, producing more energy in Michigan without buying fuel can lower costs for customers and cut reliance on fuel brought in from outside the state. DTE said the projects represent an investment in Michigan and its communities. They are also expected to generate construction employment, attract new investment and add tax revenue that helps fund schools, first responders and other services Michigan families use daily. These are the company's stated expectations for the program rather than measured outcomes.

Bid terms and timeline

The solicitation covers up to 150 MW of new Michigan-based solar and supports requirements in the settlement agreement for Michigan Public Service Commission Case No. U-21662, which was approved on May 15, 2025.

  • Projects must be located in Michigan and reach commercial operation by June 30, 2030.
  • Winning projects must interconnect to either the MISO transmission system or DTE's distribution system.
  • Proposals are due Jan. 19, 2027, and DTE expects to sign contracts in the second or third quarter of 2027.

Offering both the regional transmission network and the utility's own distribution system as connection points gives developers two routes for delivering power into the Michigan grid. Interested bidders can register and obtain further information through PowerAdvocate, the company said. The announcement did not identify specific sites, developers or cost estimates; those details would be settled through the competition.

Portfolio context

DTE describes itself as both a producer of and investor in Michigan renewable energy, with wind and solar output sufficient to serve nearly one million homes. The company is working toward net-zero carbon emissions while maintaining a balanced mix of resources intended to protect reliability and affordability.

Its 2026 Integrated Resource Plan builds on that commitment and calls for an additional 15 gigawatts of renewable capacity by 2042, a target far larger than the 150 MW now out for bid, which suggests the current solicitation is one incremental step in a longer build-out. DTE did not say how the 150 MW would be divided among winning bidders or what share would connect to transmission rather than distribution.

Reported by Mina Sato, Grid Integration, Monitoring and EV Charging Editor.