At a glance

  • The Cwm Taf programme would replace century-old treatment assets, with procurement due to begin in early 2027 under Ofwat’s Direct Procurement for Customers model.
  • Plans have been lodged for Welsh Water’s Cwm Taf scheme, described as its biggest infrastructure project, covering a new treatment works near Merthyr Tydfil and an upgrade at Llwyn-onn. Procurement is due to begin in early 2027 under Ofwat’s Direct Procurement for Customers model.
Concept illustration of a proposed water treatment works with clarifiers, storage tanks and pipelines in a green upland setting.

Plans have been lodged for Welsh Water’s Cwm Taf scheme, which the company describes as the biggest infrastructure project in its history. The scheme is intended to replace ageing treatment assets that have served the region for more than a century.

Contractors and investors are already being sounded out ahead of procurement. The procurement process is due to start in early 2027 under Ofwat’s Direct Procurement for Customers model.

The main construction package centres on a new water treatment works at Dan-y-Castell Farm near Merthyr Tydfil. Alongside the treatment works, the package includes treated water storage, a new pumping station at Pontsticill and connecting pipelines.

A second project covered by the proposals will upgrade Llwyn-onn Water Treatment Works in Bannau Brycheiniog National Park. That project is to add water storage and pipeline connections.

The published details therefore set out two treatment-related work streams: the new works and associated infrastructure near Merthyr Tydfil, and the upgrade at Llwyn-onn. They also identify the procurement route and the planned early-2027 start for procurement. The scheme is being brought forward under a model that involves contractors and investors at an early stage. The construction package and the second project are presented as proposals; the details do not state that construction has begun.

Reported by Selin Kaya, Interior Surfaces and Fit-Out Analyst.